Skip to content

case study · Energy / industry

BI energy monitoring for an industrial complex

For an industrial complex in Pavlodar Region we set up loading of power consumption data from SCADA into Power BI every 5 minutes. Engineers see usage by workshop and substation almost right away.

  • 5 mintelemetry load interval
  • 40+metering points
  • 12workshops and substations covered

Challenge

Telemetry stayed inside SCADA, and power engineers compiled consumption by workshop by hand once a month. Overruns and peak loads showed up only afterwards, on supplier invoices.

What we did

  • Designed SCADA telemetry ingestion over OPC UA through an intermediate bus
  • Built a MS SQL Server warehouse with SSIS loads every 5 minutes
  • Built dashboards for consumption by workshop, peak loads and energy use per product type
  • Prepared an operating procedure for the client IT team

Outcome

Engineers used to see consumption and peak loads only at month-end; now they see them during the day and plan load schedules ahead. Energy use per product type is used to compare shifts. The analytics never touches equipment control.

let's talk

Need a similar result?

Tell us about your task - we will prepare a technical proposal with stages, timeline and a cost estimate.